American Recovery and Reinvestment Act (ARRA) - Deicing Pad Taxiway L Project
| Project | Start Date |
Completion Date |
| Apron Reconstruction East of Spots 3 and 4 | 07/01/2011 | 02/15/2012 |
| Deicing Pad 34L | 04/25/2011 | 10/26/2012 |
| North Cargo Apron Expansion Phase 3 | 04/09/2012 | 10/05/2012 |
| Pedestrian Bridge Floor Replacement | 04/16/2012 | 07/06/2012 |
| Snow Equipment Storage Building and Access Road | 05/29/2012 | 12/21/2012 |
| T/W L Deicing Pad - Phase 2 | 04/12/2010 | 05/21/2012 |
Please CLICK HERE to be directed to the S.L.C. Online Bid System to obtain bid documents on open construction projects.
These files are in Adobe Acrobat format. If you do not have an appropriate viewer installed, you can download Adobe Reader.
Disadvantaged Business Enterprise (DBE)
Click Here to download the current DBE application (typeable)
Click Here to view the Utah Department of Transportation (UDOT) DBE Directory.